PFC Quarterly Report - Project Schedule and Expenditures
Public Agency: England Economic & Industrial Development District
Use Airport: Alexandria International Airport
Quarter Ending Date: 9/30/2004
Application Number: 99-01-C-02-AEX
Application Approval Date: 12/29/1998
Required Project Implementation Date: 12/29/2000
Implement Complete Expended
Project Est. Est. Previously Current Total Expected
ID Project Title Actual Actual Reported Quarter Cumulative Use Approval Total Cost
1 ARFF Vechicle 7/1/1999 7/1/1999 2/1/1996 2/1/1996 $343,967 $343,967 $343,967 $343,967
2a New Terminal Building-Construction 1/1/1999 1/1/1999 12/1/2005 $5,205,000 $5,205,000
2b New Terminal Building-Financing and Interest 1/1/2000 1/1/2019 $202,333 $165,374 $367,707 $3,741,875 $3,741,875
2c New Terminal Building-Pay as you go 7/1/1998 7/1/1998 5/1/1999 5/1/1999 $913,674 $913,674
3a PFC Application Fees 7/1/1998 7/1/1998 5/1/1999 5/1/1999 $34,385 $34,385 $34,385 $34,385
3b PFC Application Fees - Amendment #1 10/1/2001 10/1/2001 12/1/2001 12/1/2001 $21,026 $21,026 $21,026 $21,026
3c PFC Application Fees - Amendment #2 6/1/2003 6/1/2003 8/1/2003 8/1/2003 $22,637 $22,637 $25,000 $25,000
Application Total $624,348 $165,374 $789,722 $10,284,927 $10,284,927