PFC Quarterly Report - Project Schedule and Expenditures
Public Agency: England Economic & Industrial Development District
Use Airport: Alexandria International Airport
Quarter Ending Date: 3/31/2005
Application Number: 99-01-C-02-AEX
Application Approval Date: 12/29/1998
Required Project Implementation Date: 12/29/2000
Implement Complete Expended
Project Est. Est. Previously Current Total Expected
ID Project Title Actual Actual Reported Quarter Cumulative Use Approval Total Cost
1 ARFF Vechicle 7/1/1995 7/1/1995 2/1/1996 2/1/1996 $343,967 $343,967 $343,967 $343,967
2 New Terminal Building Program 1/1/1999 1/1/1999 4/1/2018 $363,163 $452,685 $815,848 $9,860,549 $9,860,549
3 PFC Application Fees 7/1/1998 7/1/1998 8/1/2003 8/1/2003 $78,048 $78,048 $80,411 $80,411
Application Total $785,178 $452,685 $1,237,863 $10,284,927 $10,284,927